TRANSMISSION AND GRID STATIONS PROJECTS

NTDC-KESC 500/220 kV INTERCONNECTION PROJECT (PHASE-I)

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Document and Evaluation of the Bids.

Total Project Cost - PKR 284 Million and US$ 29.3 Million
Barqaab Share - 100%
Date of Commencement - June 2003
Date of Completion - March 2004 

SCOPE OF WORK

Two Nos. 500/220kV 3x200MVA Transformer Bay.
Two Nos. 220kV Line Bays.
Two Nos. 500kV Line Bays.
5KM 500kV Transmission Line.
15KM 220kV Transmission Line.

NTDC-KESC 500/220 kV INTERCONNECTION PROJECT (PHASE-II)

500/220 kV GIS Grid station along with 500kV IN/OUT and 220kV Transmission Line Feeding KESC Network – Residency Construction Supervision Including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, Follow Up and Revision Of Construction Schedules, Monitoring and Reporting Of Progress, Variation Orders and Design Changes During Execution, Testing And Commissioning, Final Completion Report And Handing Over The Project.

Total Project Cost - PKR 284 Million and US$ 29.3 Million
Barqaab Share - 100%
Date of Commencement - October 2004
Date of Completion - December 2006

SCOPE OF WORK

Two Nos. 500/220kV 3x200MVA Transformer Bay.
Two Nos. 220kV Line Bays.
Two Nos. 500kV Line Bays.
5KM 500kV Transmission Line.
15KM 220kV Transmission Line.

500 kV MUZAFFARGARH AND GATTI TRANSMISSION LINE PROJECT

Residency Construction Supervision Including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, Follow Up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes During Execution Testing And Commissioning, Final Completion Report And Handing Over the Project.

Total Project Cost - US$ 44 Million + PKR 458.9 Million
Barqaab Share - 100%
Date of Commencement - November 2005
Date of Completion - September 2008

SCOPE OF WORK

280km 500 kV Single Circuit, Quad Bundle Transmission Line from Muzzafargarh to Gatti.

500 kV MUZAFFARGARH AND GATTI GRID STATIONS EXTENSION PROJECT

Residency Construction Supervision Including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, Follow Up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes During Execution Testing And Commissioning, Final Completion Report And Handing Over the Project.

Total Project Cost - US$ 36 Million
Barqaab Share - 100%
Date of Commencement - November 2005
Date of Completion - December 2008

SCOPE OF WORK

Muzaffargarh Grid Station

One no. complete bay of breaker and half configuration for a 500kv line and an autotransformer.
550/3kV, 3x37 MVAR Shut Reactor Bank with 1x37 MVAR spare unit.
One 525/220kV, 3x200MVA Autotransformer Bank with 1x200MVA spare unit.

Gatti Grid Station

One complete bay of breaker and half configuration for a 500kV line.
550/3kV, 3x37MVAR Shunt Reactor Bank with 1x37 MVAR spare unit.

500kV GATTI GRID STATION EXTENSION PROJECT

Total Project Cost - PKR 3500 Million
Barqaab Share - 100%
Date of Commencement - August 2009
Date of Completion - May 2010

SCOPE OF WORK

2x600MVa, 500/220kV Auto-Transformer with Controlling Switchgear on both sides.
2x250MVa, 220/132kV Auto-transformer with controlling switchgear on both sides.
2x220kV Line Bay.
1x6.3MVA, 132/11kV Power Transformer with controlling switchgear for auxiliary services.
8x132kV Line Bays and one bus coupler bay.
In and Out of 500kV Guddu-Multan 2nd Circuit at DG Khan 500kV substation (20+20KM).

500kV LAHORE (SHIEKHUPURA) GRID STATION PROJECT

Total Project Cost - PKR 917 Million
Barqaab Share - 100%
Date of Commencement - January 2008
Date of Completion - February 2009

SCOPE OF WORK

One No. 500/220kV, 3x200MVA Transformer Bay.

500/220kV DERA GHAZI KHAN SUBSTATION ALONG WITH ASSOCIATED 500KV AND 220KV TRANSMISSION LINES (PHASE-II)

Total Project Cost - PKR 3500 Million
Barqaab Share - 100%
Date of Commencement - February 2011
Date of Completion - January 2013

SCOPE OF WORK

2x600MVa, 500/220kV Auto-Transformer with Controlling Switchgear on both sides.
2x250MVa, 220/132kV Auto-transformer with controlling switchgear on both sides.
2x220kV Line Bay.
1x6.3MVA, 132/11kV Power Transformer with controlling switchgear for auxiliary services.
8x132kV Line Bays and one bus coupler bay.
In and Out of 500kV Guddu-Multan 2nd Circuit at DG Khan 500kV substation (20+20KM).

500/220kV GIS GHAZI BAROTHA GRID STATION EXTENSION PROJECT

Preparation of Bid Level Design, Bill of quantities, Technical Specifications, Tender Document, Evaluation of the Bids, Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 1.654 Million
Barqaab Share - 100%
Date of Commencement - August 2009
Date of Completion - June 2012

SCOPE OF WORK

600MVA 500/220kV Auto Transformer Bay.
Associated Civil Works Foundations, Trenches, Walk way etc.

500kV SHIKARPUR GRID STATION AND ASSOCIATED TRANSMISSION LINE PROJECT

Preparation of Bid Level Design, Bill of quantities, Technical Specifications, Tender Document, Evaluation of the Bids, Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 8,050 Million
Barqaab Share - 100%
Date of Commencement - October 2010
Date of Completion - September 2012

SCOPE OF WORK

2x600MVA, 500/220kV Transformers with allied equipment
2x500kV S/C transmission Line 20+20 = 40KM on 3 bundle Greely Conductor for looping In/Out of 500kV Dadu-Guddu Circuit No.1 at Shikarpur new.
2x500kV S/C Transmission Line 22+22=44KM on quad-Bundle Greely conductor for looping In/Out of 500kV Dadu-Guddu Circuit No.2 at Shikarpur.
220kV D/C Transmission Line 50KM long on Single Rail Conductor for looping In/Out of 220kV Guddu-Sibbi S/C Shikarpur New.
Associated Civil Works Foundations, Trenches, Walk way etc.

500kV TRANSMISSION SCHEME FOR DISPERSAL OF POWER FROM NEELUM-JHELUME HYDROPOWER PROJECT AS A JOINT VENTURE PARTNER WITH NESPAK

Preparation of Bid Level Design, Bill of quantities, Technical Specifications, Tender Document, Evaluation of the Bids, Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.  Working as Joint Venture Partner with NESPAK.

SCOPE OF WORK

235KM Long 500kV Single Circuit Transmission Line from Neelum-Jhelum to Gujranwala (Ghakkar).
110KM Long 500kV single Circuit Quad Bundle Transmission Line from Neelum-Jhelum to Rewat.
Extension by one Bay each in 500kV Substation at Rewat and Gujranwala (Ghakkar).

220kV/132kV SHALAMAR SUBSTATION (GIS) AND ALLIED 220KV D/C OVERHEAD TRANSMISSION LINE AND UNDERGROUND CABLE PROJECT (PHASE-I)

Preparation of Layout Plan, Single Line Diagram, Protection Schemes, Preliminary Civil Structure Design, Technical Specifications, Bill of Quantities and Tender Documents.

Total Project Cost - PKR 3,600 Million
Barqaab Share - 100%
Date of Commencement - November 2008
Date of Completion - July 2009

SCOPE OF WORK

3x160MVA, 220/132kV Transformer with Controlling Switchgear on both Sides.
220kV D/C Transmission Line with Line Controlling Equipment for In/Out of one Circuit of Ravi-K.S.K Transmission Line at Shalamar (9KM Long Overhead Transmission Line and 3+3KM underground Cable).
6.3MVA 13/211kV Transformer with Controlling Switchgear for Auxiliary Services.

220kV BAHAWALPUR GRID STATION EXTENSION PROJECT

Construction Supervision, Contract Management and Testing & Commissioning for Addition of 3x160MVA 220/132kV Power Transformer Along With 220kv and 132kv Allied Equipment.

Total Project Cost - PKR 309 Million
Barqaab Share - 100%
Date of Commencement - September 2008
Date of Completion - October 2009

SCOPE OF WORK

One No. 220/132kV, 3x160MVA Transformer Bay.

220kV YOUSAFWALA GRID STATION EXTENSION PROJECT

Construction Supervision, Contract Management and Testing & Commissioning for Addition of 3x160MVA 220/132kV Power Transformer Along With 220kv and 132kv Allied Equipment.

Total Project Cost - PKR 309 Million
Barqaab Share - 100%
Date of Commencement - September 2008
Date of Completion - September 2009

SCOPE OF WORK

One No. 220/132kV, 3x160MVA Transformer Bay.

220kV HALA ROAD HYDERABAD GRID STATION EXTENSION PROJECT

Construction Supervision, Contract Management and Testing & Commissioning for Addition of 3x160MVA 220/132kV Power Transformer Along With 220kv and 132kv Allied Equipment.

Total Project Cost - PKR 309 Million
Barqaab Share - 100%
Date of Commencement - September 2008
Date of Completion - October 2009

SCOPE OF WORK

One No. 220/132kV, 3x160MVA Transformer Bay.

220kV BANNU GRID STATION EXTENSION PROJECT

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project

Total Project Cost - PKR 309 Million
Barqaab Share - 100%
Date of Commencement - January 2009

SCOPE OF WORK

One No. 220/132kV, 3x160MVA Transformer Bay.
Two Nos. 220kV Line Bays.

220kV LUDEWALA GRID STATION EXTENSION PROJECT

Construction Supervision, Contract Management and Testing & Commissioning for Addition of 3x160MVA 220/132kV Power Transformer Along With 220kv and 132kv Allied Equipment.

Total Project Cost - PKR 309 Million
Barqaab Share - 100%
Date of Commencement - January 2009
Date of Completion - August 2009

SCOPE OF WORK

One No. 220/132kV, 3x160MVA Transformer Bay.
Two Nos. 220kV Line Bays.

220KV CHASHMA - LUDEWALA TRANSMISSION LINE AND EXTENSION OF 220KV LUDEWALA GRID STATION PROJECT

Preparation of Bid Level Design, Bill of quantities, Technical Specifications, Tender Document, Evaluation of the Bids, Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 2,057 Million
Barqaab Share - 100%
Date of Commencement - October 2010

SCOPE OF WORK

170KM long 220kV Double Circuit, Twin Bundle Conductor with OPGW Transmission Line between Chashma and Ludewala.
One Complete Dia (Breaker and a Half Scheme) Comprising Two Line Bays at 220kV Ludewala Substation.
PLC & OPGW Terminal Equipment, SCADA/RTU and Associated Equipment at Chashma-II Substation.
Replacement of PLC Equipment at 220kV Daud Khal Substation.

220kV GAWADAR GIS GRID STATION ALONG WITH ALLIED TRANSMISSINO LINE PROJECT

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 2,645 Million
Barqaab Share - 100%
Date of Commencement - January 2011

SCOPE OF WORK

2x250, 220/132kV Auto-Transformer.
2x220kV Dia.
1x6.3MVa, 132/11kV Power Transformer.
6x132kV Line Bays.
72KM 220kV D/C Transmission Line on “Greely” Conductor (Twin Bundle) from Iran Border to Gawadar Grid Station.

220/132kV ROHRI TO SHIKARPUR AND ROHRI TO GAMBAT TRANSMISSION LINE PROJECT

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 713 Million
Barqaab Share - 100%
Date of Commencement - January 2009
Date of Completion - June 2011

SCOPE OF WORK

62KM long 220kV Double Circuit Twin bundle Transmission Line from 220kV Rohri Grid Station to 220kV Shikarpur Grid Station.
71KM long 132kV Double Circuit Twin Bundle Transmission Line from 220kV Rohri Grid Station to 132kV Gambat Grid Station.
20KM long 132kV Double Circuit Twin Bundle Transmission Line from 220kV Rohri Grid Station to 132kV Khairpur Grid Station.

220kV D.G KHAN TO LORALAI TRANSMISSION LINE PROJECT

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 1,905 Million
Barqaab Share - 100%
Date of Commencement - September 2009
Date of Completion - September 2011

SCOPE OF WORK

Lot-I:     85KM Long 220kv Double Circuit Twin Bundle Transmission Line from D.G Khan Grid Station to 220kV Loralai Grid Station (From D.G. Khan Grid Station to Location No.261).

Lot-II:    85KM Long 220kv Double Circuit Twin Bundle Transmission Line from D.G Khan Grid Station to 220kV Loralai Grid Station (From Location No.261 to Location No.520).

Lot-III:   80KM Long 220kv Double circuit Twin Bundle Transmission Line from D.G Khan Grid Station to 220kV Loralai Grid Station (From Location No.520 to Loralai Grid Station).

220kV LORALAI GRID STATION PROJECT

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 2,500 Million
Barqaab Share - 100%
Date of Commencement - January 2011
Date of Completion - June 2012

SCOPE OF WORK

2x250MVA, 220/132kV ATFs
2x220kV Dia.
6x132kV L/Bays.
1x10/13MVA, 132/11kV PTF.
3x132kV T/Bays.

220kV ROHRI AND SHIKARPUR GRID STATION EXTENSION PROJECT

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - RMP 60 Millions PKR 177 Millions
Barqaab Share - 100%
Date of Commencement - May 2010
Date of Completion - December 2011

SCOPE OF WORK

220kV Rohri Grid Station

220kV Equipment (One and a Half Breaker Scheme)

Two Nos. Transformer Bays with 220kV MVA 220/132kV Transformers along with Allied Equipment.
Four (04) Nos. Line Bay.
Two No. Power Transformer Bay.
Telecommunication, SCADA, Protection, Control Metering and Associated Foundations (Civil Works).

132kV Equipment

Six 132kV Line Bays.
Two Nos. Transformer Bays.
Telecommunication, Protection, Control Metering and Associated Foundations (Civil Works).
Two (02) Nos. Power Transformer Bay.
One (01) No. Bus Coupler Bay.
One No. Auxiliary Transformer Bay with 6.3 MVA, 132kV/11kV Auxiliary Transformer along with Allied Equipment.

220kV Shikarpur Grid Station

220kV Equipment (One and a Half Breaker Scheme)

Two (02) Nos. 220kV Line Bays.
Bus bar works (extension) in order to accommodate one dia.
Telecommunication, SCADA, Protection, Control Metering and Associated Foundations (Civil Works).
Associated Civil Works Foundations, Trenches, Walk way etc.

220kV CHISHTIAN GRID STATION AND ASSOCIATED TRANSMISSION LINE PROJECT

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 2,633 Millions
Barqaab Share - 100%
Date of Commencement - October 2010
Date of Completion - January 2012

SCOPE OF WORK

2x160MVA, 220/132kV ATF.
2x220kV Dia.
1x6.3MVA, 132/11kV PTF.
6x132kV Line Bays.
Associated Civil Works Foundations, Trenches, Walk way etc.

220kV AIS GRID STATION AT KASSOWAL AND ASSOCIATED TRANSMISSION LINES

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - RMB 55 Millions + PKR 365 Millions
Barqaab Share - 100%
Date of Commencement - February 2010
Date of Completion - March 2012

SCOPE OF WORK

Lot-I        

Kassowal 220 kV Grid Station:
2 x 160 MVA, 220/132kV auto-transformers.
4 x 220kV line bays, 2 x 220kV transformer bays, 6 x 132kV line bays and 2 x 132kV transformer bays.
1 x 6.3 MVA, 132/11.5kV power transformer with controlling switchgear at 132kV side.
Control house building.
132kV relay building.

Lot-II    

Two Twin Bundle, Double Circuit T/Lines for In & Out of Existing 220kV Vehari-Yousafwala D/C T/Line.

220 kV KHUZDAR - DADU TRANSMISSION LINE AND EXTENSION OF GRIDSTATION AT BOTH ENDS AS A JOINT VENTURE PARTNER WITH NESPAK

Preparation of Bid Level Design, Bill of quantities, Technical Specifications, Tender Document, Evaluation of the Bids, Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

SCOPE OF WORK

300KM long 220kV Double Circuit Dadu-Khuzdar Transmission Line.
2x160MVA Auto Transformer with interfacing to existing 132kV Busbar at Khuzdar Grid Station.
Two 220kV Line Bays at Khuzdar Grid Station.

220kV WAPDA TOWN, LAHORE GRID STATION AND ALLIED TRANSMISSION LINE PROJECT

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project. Working as Joint Venture Partner with NESPAK.

Total Project Cost  - PKR 470 Million
Barqaab Share  - 100%
Date of Commencement - January 2009
Date of Completion  - June 2010

SCOPE OF WORK

220kV GIS Plant with allied Transformer and Line Bays.
3x160MVA Transformers.
20KM long 220kV D/C Transmission Line.
Associated Civil Works Foundations, Trenches, Walk way etc.

220kV/132kV SHALAMAR SUBSTATION (GIS) AND ALLIED 220kV D/C OVERHEAD TRANSMISSION LINE AND UNDERGROUND CABLE PROJECT (PHASE-II)

Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.

Total Project Cost - PKR 3600 Million
Barqaab Share - 100%
Date of Commencement - May 2010
Date of Completion - June 2012

SCOPE OF WORK

3x160MVA, 220/132kV Transformer with Controlling Switchgear on both Sides.
220kV D/C Transmission Line with Line Controlling Equipment for In/Out of one Circuit of Ravi-K.S.K Transmission Line at Shalamar (9KM Long Overhead Transmission Line and 3+3KM underground Cable).
6.3MVA 13/211kV Transformer with Controlling Switchgear for Auxiliary Services.

NATIONAL TRANSMISSION AND DESPATCH COMPANY (NTDC) CAPACITY BUILDING PROJECT

The main objective of the technical assistance was to undertake institutional capacity building of NTDC with the intent of preparing NTDC to professionally manage the power transmission, dispatch, and trading activities stipulated in its license. This institutional capacity building would develop and implement more efficient and effective information gathering, planning, and operating procedures for the transmission system operations, and the market operations of NTDC, resulting in a more efficient and transparent power sector. The output of the TA will be the

Establishment of NTDC’s business functions as per its license, as well as financial and technical segregation of said functions.

Ensure that institutional frameworks for the design and planning business segments are introduced, and

Development of an integrated training program for each business function.  Working as Joint Venture Partner with Economic Consulting Associates Limited, U.K.  Project funded by Asian Development Bank (ADB).

MULTI SECTOR REHABILITATION PROJECT AZAD JAMMU & KASHMIR (AJ&K)

Assessment Material, Preparation of Tender Documents, Evaluation and Recommendations for Award of Contract, Preparation of Layout Plans, Approval of Detailed Design for Extension and Upgradation of Distribution Network.  Project funded by Asian Development Bank (ADB). Working as Joint Venture Partner with ECIL, Karachi.

500/220kV EXTENSION OF GHAZI BAROTHA GRID STATION

Preparation of Layout Plan, Single Line Diagram, Protection Schemes, Preliminary Civil Structure Design, Technical Specifications, Bill of Quantities and Tender Documents.  Working   as Joint Venture Partner with NESPAK.

RELOCATION OF 500 kV TRANSMISSION LINE TOWER ON M-1 & M-3

Design and Construction Supervision of Relocation of 500 kV Transmission Line Towers on M-1 and M-3 Crossings.  Working as Joint Venture Partner with NESPAK.

UPGRADATION OF LOAD DESPATCH SYSTEM PROJECT

Preparation of Specification, Pre-Qualification of Bidders, Preparation of Contract Documents and Detailed Design of the Project as a Joint Venture Member.

NEW 132KV GANGAL GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

NEW 132KV MES RAWALPINDI GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

NEW 132KV ADYALA GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

NEW 132KV BEHTAR MORE GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132KV SOHAWA GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132KV NEW JHELUM GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

REPLACING EXISTING (CONVERSION) 66KV TO 132KV DANDOT GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

REPLACING EXISTING (CONVERSION) 66KV TO 132KV PINANWAL GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

REPLACING EXISTING (CONVERSION) 66KV TO 132KV AHMADAL GRID STATION PROJECT
Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

REPLACING EXISTING (CONVERSION) 66KV TO 132KV PINDI GHEB GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

REPLACING EXISTING (CONVERSION) 66KV TO 132KV HAJEERA GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

REPLACING EXISTING (CONVERSION) 66KV TO 132KV PALANDARI GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

REPLACING EXISTING (CONVERSION) 66KV TO 132KV MINHASA GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

EXTENSION OF LINE BAYS OF 132KV AZAD PATTAN GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

EXTENSION OF LINE BAYS OF 132KV C.S SHAH GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

EXTENSION OF LINE BAYS OF 132KV TARARKHAL, PIRWADAI GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

EXTENSION OF LINE BAYS OF 132KV MUREE GRID STATION PROJECT

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV RAWAT TO CHAKERI TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV BURHAN TO MARGALLA TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV TARAKHAL TO HAJEERA TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV TARARKHAL TO PALANDARI TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV AZAD PATTAN TO PLANDAO TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV CHAK SAWAI TO KOTLI TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV C.S.SHAL TO DANDOT TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV FATEH JANG TO AHMADALA TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV AHMADALA TO PINDI GHEB TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132kV DANDOT TO PINANWAL TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids of the Project Funded by the World Bank under Jurisdiction of Islamabad Electric Power Supply Company (IESCO).

132/11.5KV GRID STATION AND OVERHEAD ELECTRICAL INFRASTRUCTURE OF MULTAN INDUSTRIAL ESTATE PHASE-II

Preparation of Tender Documents, Bill of Quantities, Technical Specifications Tender Evaluation and Design of Grid Station and Overhead Electrical Infrastructure.

132kV GIS MOMINPURA GRIDSTATION ALONG WITH ASSOCIATED TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids and Construction Supervision of the Project under 6th STG project LESCO.

132kV GIS GULBERG GRIDSTATION ALONG WITH ASSOCIATED TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids and Construction Supervision of the Project under 6th STG project LESCO.

132kV GIS SAGGIAN GRIDSTATION ALONG WITH ASSOCIATED TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids and Construction Supervision of the Project under 6th STG project LESCO.

132kV GIS INAYATPURA GRIDSTATION ALONG WITH ASSOCIATED TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids and Construction Supervision of the Project under 6th STG project LESCO.

132kV GIS BARKI GRIDSTATION ALONG WITH ASSOCIATED TRANSMISSION LINE

Preparation of Bid Level Design, Bill of Quantities, Technical Specifications, Tender Documents and Evaluation of Bids and Construction Supervision of the Project under 6th STG project LESCO.

3X132KV GRID STATIONS AND 700 NEW VILLAGES ELECTRIFICATIN UNDER 2nd RURAL ELECTRIFICATION PROJECT

Preparation of Tender Evaluation and Construction Supervision of Extending Electricity Supply To 700 New Villages / Settlements And Construction Of 3x132kv Grid Stations Along With Associated Transmission Lines, for Extending Electricity Facilities to 25600 General, 70 Industrial And 200 Tubewell Consumers.